ACTD HISTORY
ATK awarded a $54M ACTD contract 2 May 96
Program initial shortcomings:
- 1st flight delayed 5 months
- Heavy fuel engine project failed
- Cost of program increased 80%
- AV required growth to improve performance
- Conversion to UEL AVGAS engine Nov 97
- Successful integration of Integrated Beacon Landing System (IBLS)
Program remained behind schedule