FY98 Program Element Descriptive Summaries / RDDS
0604739A JTT/CIBS-M (TIARA)
A. Mission Description and Budget Item Justification: The Integrated Broadcast Service (IBS) is the worldwide, DoD standard network for transmitting tactical and
strategic intelligence and targeting data. The Common Integrated Broadcast Service - Modules (CIBS-M) Joint Program (all services and SOCOM) was created to
consolidate and replace existing IBS receiver functionality/capability, inherent with the duplicative existing systems, with a "common family" of IBS modules (both
hardware and software). This is a FY 97 new start required to implement the IBS plan and consolidate/eliminate duplication of effort previously spread across multiple
PEs/SSNs DoD wide. This program funds design, development, test and evaluation of initial CIBS hardware and software modules, as well as implementing performance
expanding modifications to the family of CIBS-M equipment. This program element supports development efforts in the Engineering and Manufacturing development
phases of the Acquisition Strategy and is therefore, correctly placed in Budget Activity 5.
Acquisition Strategy: The CIBS-M family of modules will be the sole provider of IBS Modules to a variety of IBS receivers across all DOD component agencies. The
Joint Program will competitively develop hardware and software modules and procure the required modules for integration into host receiver (e.g. MATT, CTT, TRE)
systems. Additionally, this line provides for necessary modifications to IBS modules as the broadcast networks continue to evolve and modify their formats and protocols.
FY 1996 Accomplishments: Project not funded in FY 96.
FY 1997 Planned Program:
|
3359 |
Develop CIBS Module discrete designs and combinations |
|
911 |
Develop DAMA Compliant CIBS-M software module |
|
378 |
Integrate and Test DAMA Compliant software module |
|
117 |
Small Business Innovation Research/Small Business Technology Transfer (SBIR/STTR) Programs |
Total |
4765 |
|
FY 1998 Planned Program:
|
1450 |
Complete CIBS-Module prototype fabrication |
|
1644 |
Complete CIBS-Module Development |
|
1405 |
Host system integration/test |
Total |
4499 |
|
FY 1999 Planned Program:
|
2800 |
Design Next Generation CIBS-Modules |
|
799 |
Design/Develop "Over the Air" Software Load Capability |
|
848 |
Host System Integration/Test |
Total |
4447 |
|
B. Project Change Summary |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
FY 1997 Presidents Budget |
0 |
4867 |
4845 |
4819 |
Appropriated Value |
0 |
4765 |
|
|
Adjustments to Appropriated Value |
0 |
|
|
|
FY 1998 Pres Bud Request |
0 |
4765 |
4499 |
4447 |
C. Other Program Funding Summary |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
FY 2000 |
FY 2001 |
FY 2002 |
FY 2003 |
To
Compl |
Total
Cost |
V29600 JTT/CIBS-M (Tiara) |
29076 |
18991 |
11438 |
11703 |
25527 |
26450 |
12904 |
13554 |
Cont |
Cont |
BA1081 Integrated Broadcast Terminal Mod (Tiara) |
0 |
3361 |
3294 |
932 |
0 |
0 |
0 |
0 |
0 |
7587 |
D. Schedule Profile |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
|
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
1 |
2 |
3 |
4 |
Award CIBS-M Contract |
|
|
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
DAM Module Design Review |
|
|
|
|
|
|
X |
|
|
|
|
|
|
|
|
|
Prototype Test |
|
|
|
|
|
|
|
X |
|
|
|
|
|
|
|
|
Initial CIBS Module |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Preliminary Design Review |
|
|
|
|
|
|
|
X |
|
|
|
|
|
|
|
|
Critical Design Review |
|
|
|
|
|
|
|
|
|
X |
|
|
|
|
|
|
Prototype Test |
|
|
|
|
|
|
|
|
|
|
|
X |
|
|
|
|
Next Generation Module |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Preliminary Design Review |
|
|
|
|
|
|
|
|
|
|
|
|
X |
|
|
|
Critical Design Review |
|
|
|
|
|
|
|
|
|
|
|
|
|
X |
|
|
Prototype Test |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
X |
|
A. Project Cost Breakdown |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
Hardware Development |
|
2492 |
693 |
850 |
Software Development |
|
1211 |
1645 |
2471 |
Host System Integration |
|
0 |
1405 |
848 |
Technical Test |
|
740 |
541 |
173 |
Project Management |
|
205 |
215 |
105 |
SBIR/STIR |
|
117 |
|
|
Total |
|
4765 |
4499 |
4447 |
B. Budget Acquisition History and Planning Information
Performing Organizations
Contractor or
Government
Performing
Activity |
Contract
Method/Type
or Funding
Vehicle |
Award or
Obligation
Date |
Performing
Activity
EAC |
Project
Office
EAC |
Total
Prior to
FY 1996 |
FY 1996 |
FY 1997 |
FY 1998 |
FY 1999 |
Budget to
Complete |
Total
Program |
Product Development Organizations |
TBD |
C/PFF |
Feb 97 |
TBD |
TBD |
0 |
0 |
4443 |
4284 |
4342 |
Cont |
13069 |
SBIR/STTR |
|
|
|
|
|
|
117 |
|
|
|
117 |
Support and Management Organizations |
CECOM |
MIPR |
|
|
|
|
0 |
205 |
215 |
105 |
|
525 |
Test and Evaluation Organizations: None |
Government Furnished Property: None
Subtotal Product Development |
|
|
4560 |
4284 |
4342 |
|
13186 |
Subtotal Support and Management |
|
|
205 |
215 |
105 |
|
525 |
Subtotal Test and Evaluation |
|
|
|
|
|
|
|
Total Project |
|
|
4765 |
4499 |
4447 |
|
13711 |